Sign In Get Started

Schedule of Rates in Construction: How to Prepare, Price, and Use an SOR for Tendering

#construction cost estimation #Construction Contracts
Schedule of Rates Construction: Complete SOR Guide
Yozafy
Premium Pet Products
Quality Delivered Worldwide
🐾 🐾 🐾
Everything Your Dog and Cat Needs — In One Place
Toys beds grooming harnesses water fountains and more. Premium quality products shipped directly to your door.
Free Shipping in the US Premium Quality Secure Checkout
Shop Now at Yozafy.com
yozafy.com

A facilities management contractor tendered for a three-year term maintenance contract covering a portfolio of commercial buildings in central Manchester. The contract was priced on a Schedule of Rates — a document listing every likely maintenance activity with a unit rate against each one. The contractor priced each rate carefully, built in realistic overheads and profit, and submitted a competitive tender. The contract was awarded.

In the first six months, the work distribution looked roughly as expected. Minor repairs, planned maintenance visits, small plumbing jobs. Each item measured against the SOR, each invoice calculated by multiplying the quantity of work by the agreed unit rate. The commercial model was working as the contractor had planned.

Advertisement

Then the client instructed a significant drainage clearance programme across twelve buildings — a reactive programme triggered by persistent blockage problems that had been identified during the routine maintenance visits. The drainage clearance item in the SOR had been priced at a rate the contractor calculated assuming it would represent perhaps five percent of the total contract value. Over the next four months, it represented thirty-eight percent.

The rate itself was not wrong. It covered the direct cost of the work and a reasonable margin at the volume the contractor had assumed. At nearly eight times that volume, the economics of the rate changed completely — the supervision cost per unit increased because the drainage crew needed more coordination than the rate had allowed for, the plant hire utilisation was lower than assumed, and the contribution to head office overheads from this item alone was being diluted by the volume. The contractor finished year one of a three-year contract having lost money on the item that represented more than a third of its turnover.

The lesson was not that the SOR format was wrong for this contract. It was the right format — the scope was genuinely variable and the BOQ approach would not have worked. The lesson was that pricing a Schedule of Rates requires a different discipline from pricing a BOQ. When quantities are unknown, the rate has to work at multiple volume levels — not just the one the contractor assumed when they sat down to price the tender.

 

What a Schedule of Rates Is and Why Construction Uses It

A Schedule of Rates is a contract document that lists items of work with a unit rate against each one but without any stated quantities. The client and contractor agree the rates at tender stage. Once the contract is running, work is instructed, measured as it is completed, and paid by multiplying the actual quantity by the agreed SOR rate. The total contract value is not known at the time of award — it emerges from the actual volume of work instructed and carried out.

The reason the construction industry uses the SOR format — rather than always using a BOQ with measured quantities — is that for certain types of work, the scope genuinely cannot be quantified in advance. A term maintenance contract covering reactive repairs across a large asset portfolio does not have a predictable scope. An infrastructure maintenance programme covering roads, drainage, and structures responds to conditions on the ground rather than a predetermined list of activities. An early works contract starting before the full design is complete cannot be priced against quantities that do not yet exist.

For all of these situations, the SOR provides a structured commercial framework that allows the work to proceed, the contractor to be paid fairly for what they complete, and both parties to manage cost transparently against pre-agreed unit rates rather than renegotiating prices every time a new piece of work is instructed.

The types of construction work most commonly priced on a Schedule of Rates:

       Term maintenance and facilities management contracts: Reactive maintenance, planned preventive maintenance, and minor works programmes where the volume and mix of activities changes with asset condition rather than a fixed programme

       Framework agreements: Long-term contractor appointment arrangements covering multiple projects over several years — individual call-off orders priced using framework SOR rates

       Infrastructure maintenance: Highway maintenance, drainage, structures, and utilities works where the scope is driven by inspection findings and network condition rather than a designed project

       Early contractor involvement contracts: Where the contractor is appointed before design is complete and the scope is defined progressively — SOR rates provide the commercial basis for pricing work packages as they are issued

       Measured term contracts: Formal contract arrangements — sometimes using JCT Without Quantities or NEC Option E — where all work over the contract period is valued against a pre-priced schedule

 

 

Schedule of Rates vs Bill of Quantities — The Key Differences

The BOQ and the SOR are the two primary pricing documents used in construction tendering — and understanding the difference between them determines which is the right instrument for any given project or contract. The distinction goes deeper than simply whether quantities are included or not — it affects where the risk sits, how payment is calculated, and how variations are valued throughout the contract.

 

 

Schedule of Rates (SOR)

Bill of Quantities (BOQ)

Quantities in document

No — rates only, no quantities stated

Yes — measured quantities form part of the contract

When scope is known

Type of work known, quantities unknown or variable

Scope and quantities fully defined from drawings

Contract risk on quantities

Contractor — quantities not guaranteed

Employer — quantities in BOQ are contractually stated

Best suited for

Maintenance, term contracts, reactive works, early-stage projects

New build, refurbishment with complete design, competitive tender

Tender basis

Contractor prices unit rates — no quantities to price against

Contractor prices against measured quantities provided by QS

Payment mechanism

Measured as work is done — actual quantities x agreed rates

BOQ quantities used as basis — remeasured if contract allows

Variation pricing

Straightforward — apply the agreed SOR rate to additional items

New rates needed if work type not in BOQ — can cause disputes

Final account

Measured at completion — total = actual quantities x SOR rates

BOQ quantities adjusted for variations and remeasurement

Contractor pricing risk

Must price rates that work across all possible quantity levels

Quantities are provided — risk is in the rate accuracy only

Used in contract forms

JCT Without Quantities, NEC Option E, measured term contracts

JCT With Quantities, FIDIC Red Book, traditional lump sum

 

The contractor pricing risk row in that table is the one that catches most contractors out on their first significant SOR contract. When pricing a BOQ, the QS receives quantities from the client's quantity surveyor and prices rates against them — the risk is whether the rates are competitive and accurate, not whether the quantities are correct. When pricing a Schedule of Rates, there are no quantities to price against. The contractor must decide what rate to apply to each item knowing that the volume of that item could be anything from negligible to dominant. The drainage clearance contractor in Manchester priced a rate that was commercially sound at low volume. The SOR gave the client the contractual right to instruct that item at any volume — and the rate had to work at all of them.

 

How to Build Up a Unit Rate for a Schedule of Rates

The unit rate in a Schedule of Rates is not just a price — it is a commercial position. It covers every cost associated with completing one unit of that work item, including a contribution to overheads and a profit margin, at a level that remains viable across the range of volumes that item might represent in practice. Building up rates correctly is the skill that separates contractors who make money on SOR contracts from those who discover the problem in year two.

 

Rate Component

What It Covers

Calculation Basis

Materials

Cost of materials required per unit of work — including waste allowance and delivery

Current supplier price + waste factor (typically 5–15% depending on material type)

Labour

Cost of operatives to complete one unit of work — at the productivity rate achievable on this project type

Operative hourly rate ÷ units per hour — adjusted for site conditions

Plant

Equipment required per unit — hired or owned — apportioned to this work type

Plant hire rate × time per unit, or owned plant depreciation + running cost

Subcontractor element

Where specialist work is involved — subcontractor rate plus main contractor mark-up

Subcontractor quote + 5–10% attendance and profit margin

Site overheads

Proportion of site running costs attributable to this work type — supervision, welfare, temporary services

Calculated as percentage of direct cost — typically 8–12%

Head office overheads

Contribution to company-level costs — management, finance, IT, premises

Company overhead percentage applied to direct cost — typically 3–6%

Profit

Return on the work — reflects competition level and strategic value of the contract

Percentage on cost — typically 2–5% on competitive tenders, higher on negotiated work

Risk allowance

Contingency for quantity uncertainty — items where volume is unpredictable may carry a higher rate

Assessed individually — high-volume-risk items carry more than low-risk items

 

📌  The volume stress test every SOR rate needs before submission: For each significant item in the Schedule of Rates, calculate what happens to the rate's profitability if that item represents five percent of the contract value, fifteen percent, and thirty percent. If the rate breaks down at high volume — because supervision cost per unit increases, or plant utilisation drops, or the overhead recovery becomes inadequate — either the rate needs to be higher or the risk needs to be acknowledged and managed contractually. A rate that works at five percent but loses money at thirty percent is a rate that is waiting for the wrong contract to find it.

 

The Overhead Recovery Problem at Scale

The most subtle pricing risk in a Schedule of Rates is the overhead recovery assumption. When a contractor builds overheads into an SOR rate, they are assuming that this item will contribute to overhead recovery in proportion to its share of the total work. If the item ends up representing a much larger share than expected, the overhead recovery per unit may look adequate — but the absolute overhead recovery across the whole contract may still be insufficient because the total contract value has not grown proportionally with the volume of this one item.

This happens most often on items where the rate is kept low to win the contract — competitive pressure drives the rate down on high-profile items that the client scrutinises most carefully during tender evaluation. Those same items, if instructed at high volume, end up cross-subsidising the contract's overhead recovery without delivering the margin the contractor assumed was built into the higher-rate items that were instructed at lower volume than expected.

 

What a Schedule of Rates Document Contains

A well-structured Schedule of Rates document goes beyond a list of items and rates. It contains the commercial and technical framework that both parties need to administer the contract correctly throughout its life — measuring work accurately, pricing variations that are not in the original schedule, and settling the final account without dispute.

The key sections every SOR document should include:

       Preamble and general conditions: Defines what the rates include and exclude — whether plant, supervision, and small tools are deemed included in all rates, or priced separately — this section prevents the most common SOR disputes

       Daywork schedule: Rates for labour, plant, and materials on a time and materials basis — used when work cannot be measured against the standard SOR items — typically expressed as a percentage addition to published daywork schedules

       Measured work items: The main body of the SOR — items grouped by trade or work type, each with a unit of measurement, a brief description, and the priced unit rate

       Provisional and star rate items: Items where the rate is not yet agreed — either provisional rates subject to negotiation or star rate items to be priced when the scope of that work is defined

       Percentage adjustments: Some SOR contracts allow the contractor to apply a percentage addition or deduction to a published standard schedule — such as the PSA Schedule of Rates — rather than pricing individual rates from scratch

       Escalation provisions: For contracts running longer than eighteen months, the mechanism for adjusting rates annually based on published indices — typically BCIS labour and materials indices

 

 

Using the SOR During the Contract — Valuation, Variations, and Final Account

Once the contract is running, the Schedule of Rates becomes the commercial reference for everything — monthly valuations, variation pricing, and final account settlement. A well-maintained SOR makes all three of these processes straightforward. An SOR that is poorly administered creates disputes at every stage.

Monthly Valuation Against the SOR

Each month the contractor measures the work completed during the period and applies the relevant SOR rates to calculate the valuation. The measurement must be done carefully — the preamble defines exactly what is included in each rate, and any attempt to claim separately for items the preamble says are included in the rate will be challenged by the client's QS. The measurement sheets, showing the location, description, and quantity of each item claimed, are the primary supporting document for the monthly payment application.

The client's QS checks the measurement against site records — visit reports, photographs, job cards, or whatever the contract's quality and monitoring requirements specify. Discrepancies between the contractor's measurement and the client's site records are the most common source of payment disputes on SOR contracts. The contractor who maintains clear site records, matched to SOR items and supported by evidence of completion, is the contractor who gets paid accurately and promptly.

Pricing Variations and New Items

When the client instructs work that is not covered by an existing SOR item — a new activity type, a specification requirement not anticipated in the original schedule, or a location with conditions that make the standard rate inapplicable — a new rate must be agreed. The SOR preamble should define the method for agreeing new rates — usually by reference to the build-up of the nearest comparable SOR item, adjusted for the differences in scope, materials, or method.

This is where the quality of the original rate build-up matters commercially. A contractor who can produce a transparent rate build-up for every item in the SOR — showing materials, labour, plant, overheads, and profit separately — is in a strong position to negotiate new rates based on the same methodology. A contractor who priced the SOR as a single number without a documented build-up has no reference point for the negotiation and will find the client's QS driving the new rate to the lowest defensible level.

The SOR is the commercial foundation for every variation on a term or maintenance contract. For a detailed guide to how variations are raised, valued, and managed throughout construction — whether the contract is priced on an SOR or a BOQ — see our article on Variation Orders in Construction: A Practical Guide.

 

Manage your SOR contracts alongside your BOQ and project documents

 

PlanEsti gives quantity surveyors and project managers the tools to structure pricing documents, track variations, and maintain the measurement records that keep SOR contracts commercially accurate from first instruction to final account.

 

→ Explore PlanEsti

 

Share this article

Engineer

About Engineer

Founder & CEO | PlanEsti

Frequently Asked Questions

Comments (0)

Leave a Comment

No comments yet. Be the first to comment!

Subscribe to Our Newsletter

Get the latest articles delivered straight to your inbox

JD

John D. from New York

Just subscribed to Pro Plan